Earthworks scope completed to drawings specified levels within site boundary. Excavation of material to Foundation Level for Foundation Treatment as per RMS R44 specification Subgrade excavation and fill to required Level, including proof role test on subgrade. Supply, placing & compacting pavement layers as per drawings and specifications.
-OSD tank bulked and compacted as per specification with marker layer capping. Stormwater installation with pits and pipes completed with back fill materials and adequate compaction achieved as per plan.