- Dozer push material to level the site - Backfill from foundation level to subgrade level at max 300mm layer as per standards - Geotech testing and as-built each layer as per standards - Material import to form the SMZ as per design requirements - Material import to replace and soft spots as per client?s instructions
- Complete the fill to designed RL ready for spray & seal - Organised spray & seal before Christmas to complete the civil works package, ensure the clients have the site ready for the next year